History: 2003: Connecting bridge Offshore platform Kizomba

The client required a connecting bridge and a work pontoon on the Caland Canal to complete an offshore platform.

Janson Bridging installed a Heavy Girder bridge, hinged to the work pontoon on the waterside and slid onto the bank on the landside.

The bridge had a length of 38 meters and a driving width of 6 meters.

Share on:

Projektdata

Lösning
Fackverksbro
Typ
JPB-T
Total längd
38,1 meter
Fri brobredd
5,7 meter
Egenvikt
118 ton
Design load
Vehicle 50 tons
Date of installation
January 2003
Dismantling date
November 2003