Pedestrian bridge 106x3m Nieuwegein

In 2016, the combination 'Sas van Vreeswijk BV' was awarded the contract for the design, construction, maintenance and financing of a third lock and widening of the Lekkanaal.

For this purpose, a ramp was needed to divert light traffic on site. A temporary bicycle bridge was chosen over the new lock bell to be constructed, from the lock to the Kazernedok, a local road.

Janson Bridging constructed a bicycle bridge from stock with a total length of 106 metres, consisting of three partial spans of 39, 33 and 33 metres.

Share on:

Projektdata

Lösning
Gångbro
Typ
JPB-P
Total längd
106 m (35 bays)
Fri brobredd
3 m
Egenvikt
105 ton
Design load
5 kN/m²
Date of installation
September 2016
Rental period
10 months
Installation time
3 days